What's the Best Hot Tub

Author Topic: curing a concrete pad  (Read 2093 times)

lovejoyland

  • Junior Member
  • *
  • Posts: 24
curing a concrete pad
« on: April 23, 2017, 08:14:13 pm »
Hi Everyone,

I had my contractor level out our existing concrete pad with more concrete on Thursday. Our tub was delivered Saturday afternoon, and we were hoping to fill it on Monday, but my mom told me I should wait at least a week before filling it to let the concrete cure. What do you guys think? Our contractor thought it would be fine by Monday, but he doesn't have a lot of hot tub experience. Please let me know.

Thanks!
Vanessa

Hot Tub Forum

curing a concrete pad
« on: April 23, 2017, 08:14:13 pm »

MikeK157

  • Junior Member
  • *
  • Posts: 70
Re: curing a concrete pad
« Reply #1 on: April 23, 2017, 08:35:36 pm »
Just had my pad poured 3 weeks ago and our contractor recommended a week for curing.

Tman122

  • Ultimate Member
  • *****
  • Posts: 4424
  • If it Ain't Broke
Re: curing a concrete pad
« Reply #2 on: April 24, 2017, 03:44:54 pm »
Hi Everyone,

I had my contractor level out our existing concrete pad with more concrete on Thursday. Our tub was delivered Saturday afternoon, and we were hoping to fill it on Monday, but my mom told me I should wait at least a week before filling it to let the concrete cure. What do you guys think? Our contractor thought it would be fine by Monday, but he doesn't have a lot of hot tub experience. Please let me know.

Thanks!
Vanessa

Depends on what he did Vanessa, You say he leveled your existing pad. Did he use a thin set type concrete?
Retired

Hot Tub Forum

Re: curing a concrete pad
« Reply #2 on: April 24, 2017, 03:44:54 pm »

 

Home    Buying Guide    Featured Products    Forums    Reviews    About    Contact   
Copyright ©1998-2024, Whats The Best, Inc. All rights reserved. Site by Take 42